DOT Secretary Anthony Foxx and U.S. Senator Orin Hatch (R-Utah) attended the grand opening of the fifth and final rail line of Utah Transit Authority's (UTA) Frontlines 2015 Program, two years ahead of schedule and $300 million under budget.

Frontlines is composed of four TRAX light rail transit (LRT) extensions and the Frontrunner commuter rail line, totaling 70 miles of new rail lines. The newest LRT extension is the 3.8 mile Draper Hall line to Salt Lake City's southern suburb of Draper, population 42,000 (2012, Factfinder, Census.gov).
[Draper was preparing early for the new LRT line, as we noted here in 2008, "TOD Gets Green Light in Utah"].
Covering the August 16 grand opening ceremony for Deseret News was Jasen Lee.
The extension is the final project of UTA’s FrontLines 2015 rail program. Construction for the project began in 2008 and included five (sic) light rail lines: the $370 million West Valley extension (Green Line), the $535 million Mid-Jordan line (Red Line), the $350 million Airport line (Green Line) and the $143 million Draper TRAX extension on the Blue Line, along with the $850 million FrontRunner South commuter rail line from Salt Lake City to Provo.
"We're working with local communities to make sure that we are doing everything we can to streamline the process to help other communities achieve their transit projects not only on time, but also under budget," DOT Secretary Anthony Foxx told the crowd.
Coverage of the event can also be found on the US DOT website. They note that the "Federal Transit Administration (FTA) committed $116 million for the Draper extension through its New Starts Capital Investment Grant Program... FTA committed approximately $545 million in total to the Frontlines 2015 Program, which includes $90 million through the American Recovery and Reinvestment Act."
Local funds for Frontlines projects were provided by county sales taxes.
In November 2006, Utah County and Salt Lake County residents voted to increase their sales tax by one-quarter of a cent, enabling accelerated delivery of these projects. [June 2011, Metro Magazine]
FULL STORY: Draper TRAX extension embarks this weekend

Alabama: Trump Terminates Settlements for Black Communities Harmed By Raw Sewage
Trump deemed the landmark civil rights agreement “illegal DEI and environmental justice policy.”

Study: Maui’s Plan to Convert Vacation Rentals to Long-Term Housing Could Cause Nearly $1 Billion Economic Loss
The plan would reduce visitor accommodation by 25% resulting in 1,900 jobs lost.

Why Should We Subsidize Public Transportation?
Many public transit agencies face financial stress due to rising costs, declining fare revenue, and declining subsidies. Transit advocates must provide a strong business case for increasing public transit funding.

Paris Bike Boom Leads to Steep Drop in Air Pollution
The French city’s air quality has improved dramatically in the past 20 years, coinciding with a growth in cycling.

Why Housing Costs More to Build in California Than in Texas
Hard costs like labor and materials combined with ‘soft’ costs such as permitting make building in the San Francisco Bay Area almost three times as costly as in Texas cities.

San Diego County Sees a Rise in Urban Coyotes
San Diego County experiences a rise in urban coyotes, as sightings become prevalent throughout its urban neighbourhoods and surrounding areas.
Urban Design for Planners 1: Software Tools
This six-course series explores essential urban design concepts using open source software and equips planners with the tools they need to participate fully in the urban design process.
Planning for Universal Design
Learn the tools for implementing Universal Design in planning regulations.
Smith Gee Studio
Alamo Area Metropolitan Planning Organization
City of Santa Clarita
Institute for Housing and Urban Development Studies (IHS)
City of Grandview
Harvard GSD Executive Education
Toledo-Lucas County Plan Commissions
Salt Lake City
NYU Wagner Graduate School of Public Service