Cost Overruns and Delays Causing Drama on Maryland's Purple Line

Project documents acquired by The Washington Post reveal numerous unresolved problems with construction on the Purple Line.

1 minute read

January 11, 2019, 8:00 AM PST

By James Brasuell @CasualBrasuell


Maryland Transit Administration

Maryland Department of Transportation / Purple Line Alignment

"The opening of Maryland’s Purple Line is at least a year behind schedule, and delays have added at least $215 million to the light-rail line’s cost," reports Katherine Shaver.

Now the Purple Line is expected to open in February 2023, "almost a year behind the March 2022 opening date in the project’s contract and four months behind the October 2022 date that Maryland transit officials insist is still possible," according to Shaver.

Apparently there is still dispute over the potential opening data. State transportation officials are pushing Purple Line Transit Partners (PLTP), "a team of companies building the 16-mile line and helping to finance its construction," to accelerate work to stick closer to the original schedule. Meanwhile, contractors have also proposed a much later opening date of June 2024.

There are $5.6 billion reasons for PLTP and the state to figure out a way to get on the same page. "PLTP and the state signed a $5.6 billion contract — one of the largest ever in Maryland — for the private consortium to design and build the line and then operate and maintain it for 30 years. PLTP also is helping to finance the line’s $2.4 billion construction," according to Shaver.

Thursday, January 10, 2019 in The Washington Post

portrait of professional woman

I love the variety of courses, many practical, and all richly illustrated. They have inspired many ideas that I've applied in practice, and in my own teaching. Mary G., Urban Planner

I love the variety of courses, many practical, and all richly illustrated. They have inspired many ideas that I've applied in practice, and in my own teaching.

Mary G., Urban Planner

Get top-rated, practical training

Wastewater pouring out from a pipe.

Alabama: Trump Terminates Settlements for Black Communities Harmed By Raw Sewage

Trump deemed the landmark civil rights agreement “illegal DEI and environmental justice policy.”

April 13, 2025 - Inside Climate News

High-rise apartment buildings in Waikiki, Hawaii with steep green mountains in background.

Study: Maui’s Plan to Convert Vacation Rentals to Long-Term Housing Could Cause Nearly $1 Billion Economic Loss

The plan would reduce visitor accommodation by 25% resulting in 1,900 jobs lost.

April 6, 2025 - Honolulu Civil Beat

Blue and white Seattle Link light rail train exiting concrete Downtown Bellevue Tunnel in Bellevue, WA.

Why Should We Subsidize Public Transportation?

Many public transit agencies face financial stress due to rising costs, declining fare revenue, and declining subsidies. Transit advocates must provide a strong business case for increasing public transit funding.

April 7, 2025 - Todd Litman

Silhouette of man holding on to back of bicycle ridden by woman with Eiffel Tower in background.

Paris Bike Boom Leads to Steep Drop in Air Pollution

The French city’s air quality has improved dramatically in the past 20 years, coinciding with a growth in cycling.

7 hours ago - Momentum Magazine

Multifamily housing under construction.

Why Housing Costs More to Build in California Than in Texas

Hard costs like labor and materials combined with ‘soft’ costs such as permitting make building in the San Francisco Bay Area almost three times as costly as in Texas cities.

7 hours ago - San Francisco Chronicle

Western coyote looking at camera in grassy field.

San Diego County Sees a Rise in Urban Coyotes

San Diego County experiences a rise in urban coyotes, as sightings become prevalent throughout its urban neighbourhoods and surrounding areas.

April 14 - Fox 5